143 Civil Engineering Valuation Based Permits.
Permit fees for Drainage Facilities, Landscaping, and all other right-of-way projects not listed above are based on the valuation of the project.
Project Valuation |
Permit Fee |
---|---|
$1.00—$5,000.00 |
$300.00 Base fee only* |
$5,001.00—$10,000.00 |
$51.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
$10,001.00—$50,000.00 |
$20.00 Base fee plus $46.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
$50,001.00—$100,000.00 |
$120.00 Base fee plus $44.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
$100,001.00—$500,000.00 |
$320.00 Base fee plus $42.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
$500,001.00—$1,000,000.00 |
$1,320.00 Base fee plus $40.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
Over $1,000,000.00 |
$3,320.00 Base fee plus $38.00 for each $1,000.00 or fraction thereof on the total amount of the project valuation* |
*A $150.00 charge for one hour of As-Built Review costs will be added to all drainage facilities permits and on landscape permits for work that will be publicly maintained.
EXAMPLE OF A PERMIT FEE CALCULATION: The following is an example of a permit fee calculation assuming a total project valuation of $150,500.00: $320.00 base fee plus $6,342.00 on the project valuation = Total permit fee cost of $6,662.00 (Ord. No. G-5458, § 1(Exh. A), 2009; Ord. No. G-5472, § 1(Exh. A), 2010)